Low down progress

On Saturday we managed a few jobs that are about as low as we can get.

Water getting low in the wrong places

During the heavy rain on Friday we discovered a key source of the water in the (very deep) bilge at the aft end of the keel. I’d left a few holes in the floor of the anchor locker when we had removed the old windlass and chain guide. So water getting into the anchor locker was falling into the chain locker, from there it flowed down a hose (so that it gets past the shower sump) onto the front end of the keel (where we had cut the old hose so for the first time we could see the water coming in, when we had the floor up).

So I filled the holes and we went down in the depths (currently about 1m below the electric motor frame) and pumped out 5 buckets of water (we had removed a lot more with a temporary bilge pump a few weekends ago).

Battery storage on the keel

With a dry bilge we did some cutting and planing of the battery box we had started months ago (when the 120AH batteries were going to have to sit above the motor). It now fits on the keel under the companionway and saloon floor.

It just needs ply ends, epoxy coating and the batteries installing. A battery box for the 4 x 300AH will sit on top of it (one of these batteries will be behind this and a bit higher as it is behind the ladder and the space is not wide enough at that point).

Fortunately all the lower 120AH batteries and the 300AH at the aft end have bluetooth enabled BMS (battery monitoring systems) as these will be quite inaccessible. The other 3 x 300AH will be easily visible to check.

We will make these boxes as watertight as we can and they will be fixed in place so that there is no danger of a couple of hundred kilo’s of battery smashing everything and everyone should we ever be rolled over.

We have also done some detailed design work for how we plan to connect the battery banks. We are (seemingly unusually) planning to keep them entirely separate as it isn’t a good idea to combine different sizes of battery into a single bank. We want the flexibility of using each bank for either house or motor depending on need. However, never both connected to either house or motor at the same time. We also want to be able to direct the solar panel charging to either bank according to need. The 70A mains charger built into the Victron MultiPlus II will always go to whichever bank is connected to house (so when we connect to mains we always put the most depleted bank as the house to get charged first) .

Water in the right places

We think we can fit a 70 litre water tank in front of the batteries and an 18 litre one in front of that. Plus another 18 litre tank under the aft most 300AH battery. Finally one more 18 litre tank in the forward top half of the bilge under the motor.  That makes 124 litres nice and low down that will all be fully plumped in (you get a set of taps to choose which tank the water comes from for a tap or the shower).

In addition we think we can fit 4 x 25 litre portable water tanks above the propeller shaft aft of the motor. As well as taking us to 224 litres in total, these will be convenient for collecting water in the dinghy (providing we take a trolley to save carrying them by hand).

This should be plenty of water for coastal cruising but we still need more (and would like a watermaker) for ocean crossings.

Dave not getting stuck in the bottom

Using a temporary “ladder” I went into the cockpit locker to check the setting on the dehumidifier and the position of the forward mizzen chainplate.

Low on money

Well not so much low as actually sitting down to price all the things we need to be able to launch in March 2022 (in time for a 3 month sabbatical). It is a long list, however, it looks manageable and there are not so many unknowns now. Actually a bit of a confidence builder.

Lower Mast

Next will be back to tasks to get the mizzen mast (the lower one) back up but with dyneema rigging. In part that is to prove the chainplate and rigging design but also so that we can sort out the windvane self-steering, pushpit and aft solar panels. We still need to finish the new supports for the foot of the mizzen mast, cut and fit the backing plates for the forward stays and running backstays. Also need to finish repairing the pillar drill to make the tangs (and order the bolts for them). Then we can add the FR4 backing plates (and the on deck “mushrooms”, do the drilling for the chainplate dyneema loops and then make all the chainplate loops and shrouds/stays.

All that will allow us to finish the aft cabin, at least for the moment. The bed head needs finishing as it is part of the mizzen mast foot support. We need the step onto the seat to get to the bed, cabin sides need insulating (ceiling etc can wait as can the headlining). Then a quick paint and we can move back in (hopefully the work Jane is doing at home to remodel the bed mattress will be finished).

2 thoughts on “Low down progress

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.